We are focusing on exploring a new driving force for growth by concentrating
on diversification of business such as overseas resources development, engineering business etc.

Engineering Business

Power Plants

Based on professional technical skills, we have performed the planned preventive maintenance for power generating
facilities since we were certified as a company eligible for maintenance of 5 power plants

and are registered as a partner for power plants and have actively performed construction and
the follow-up management with the best quality.

We have made the best effort for customer satisfaction on the basis of

every sort of machine tools and process technologies, diverse design experiences and know-how of constructing plants Kyungdong has.

Major Projects

No. Equipment Specification Quantity Client Completed
8 Power Plant Deck Installation 2.2x3.3m etc. 1 Lot Korea East-West Power Co., Ltd. Donghae Bio Power Jul 2018
7 Bushing Chain part production Link(190x425x125) etc. 1 Lot Korea East-West Power Co., Ltd. Donghae Bio Power Jan 2018
6 Compressor replacement 80HPx2unit etc. 1 Lot Korea East-West Power Co., Ltd. Donghae Bio Power Jan 2018
5 Metropolitan Water Fog System High-pressure pipe(100bar) 1 Lot Korea Southern Power Co., Ltd. Samcheok Power Division Feb 2018
4 Coal handling B/C Safety Facilities Protection etc. 1 Lot Korea East-West Power Co., Ltd. Donghae Bio Power Fab 2019
3 Planned Preventive Maintenance Silo 3A, 4A Replacement etc. 1 Lot Korea East-West Power Co., Ltd. Donghae Bio Power Dec 2018
2 Motor Disassemble & Convenience Facilities Low pressure Motor etc. 1 Lot GS Donghae Power Apr 2019
1 Return Idler etc. Ø140xL1,362mm etc. 1 Lot Korea East-West Power Co., Ltd. Donghae Bio Power Apr 2018
12